Oracle Primavera - PM6 Member for 24 years 4 months Member for 24 years 4 months Submitted by Andrew Pearce on Tue, 2007-04-03 06:47 Permalink RE: Different color activities Yes it can be done but you have to set up individual bars for each group. View, Bars then add new bar and use filter to select activities. Member for 20 years 8 months Member for 20 years 8 months Submitted by Bijaya Bajracharya on Tue, 2007-04-03 06:29 Permalink RE: Different color activities Format bars. Log in or register to post comments
Member for 24 years 4 months Member for 24 years 4 months Submitted by Andrew Pearce on Tue, 2007-04-03 06:47 Permalink RE: Different color activities Yes it can be done but you have to set up individual bars for each group. View, Bars then add new bar and use filter to select activities.
Member for 20 years 8 months Member for 20 years 8 months Submitted by Bijaya Bajracharya on Tue, 2007-04-03 06:29 Permalink RE: Different color activities Format bars.
Member for
24 years 4 monthsRE: Different color activities
Yes it can be done but you have to set up individual bars for each group.
View, Bars then add new bar and use filter to select activities.
Member for
20 years 8 monthsRE: Different color activities
Format bars.