Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

P3-P5-P3 export-import

1 reply [Last post]
Aydin Valiyev
User offline. Last seen 4 years 32 weeks ago. Offline
Joined: 27 Mar 2005
Posts: 6
Groups: None
Dear All,

I have a problem with P3-P5-P3 export-import:

When I import P3 file to P5 and export again to P3 in some activities in P3 accurs resource duration. Usually one day less than activity remaining duration. Also in some activities’ Budgeted Quantyties also reduces.

If somebody knows how to solve this, please share.

Kind Regards,
Aydin

Replies

Rodel Marasigan
User offline. Last seen 2 hours 26 min ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Aydin,

Have you check your unit format and hours per time period on user preference and admin preferences. By default P5 don’t adopt imported p3 files setup so you need to make sure that P5 have the same setup before importing and exporting.

Rodel