Simple because P5 storing hrs and not days. Even you change your parameter in user’s preference into day it will not convert hrs to day on calculation. There is a good discussion in this thread (http://www.planningplanet.com/forum/forum_post.asp?fid=1&Cat=8&Top=28096) explained by Ronald Winter.
Member for
19 yearsRE: Claim Digger Reports?
Hi Richard,
Simple because P5 storing hrs and not days. Even you change your parameter in user’s preference into day it will not convert hrs to day on calculation. There is a good discussion in this thread (http://www.planningplanet.com/forum/forum_post.asp?fid=1&Cat=8&Top=28096) explained by Ronald Winter.
Regards,
Rodel