Claim Digger Reports?

1 reply [Last post]
Richard Asiimwe
User offline. Last seen 16 years 12 weeks ago. Offline
Joined: 12 Feb 2007
Posts: 18
Groups: None
Why is that when you run claim digger, the report shows total float in hours even when the settings are in days? Is there something I am not doing right?

Replies

Rodel Marasigan
User offline. Last seen 2 hours 19 min ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Hi Richard,

Simple because P5 storing hrs and not days. Even you change your parameter in user’s preference into day it will not convert hrs to day on calculation. There is a good discussion in this thread (http://www.planningplanet.com/forum/forum_post.asp?fid=1&Cat=8&Top=28096) explained by Ronald Winter.

Regards,
Rodel