Actual, Budgeted, Remaining Early & Late units

3 replies [Last post]
Karim Mounir
User offline. Last seen 9 years 36 weeks ago. Offline
Joined: 5 Apr 2006
Posts: 314
Groups: None
Hi,

I made a revised target schedule and i want to clarify some info here regarding the resource distribution (used in Tracking layout in p5):

1- The Actual units shall remain the same.
2- The Budgeted units will distribute the total units along the revised duration of the schedule.
3- The remaining units (early or late) shall distribute the difference between the actual units at a certain data date & the total remaning units.

Can u justify this?

Regards.

Replies

Karim Mounir
User offline. Last seen 9 years 36 weeks ago. Offline
Joined: 5 Apr 2006
Posts: 314
Groups: None
Hi Alex,

I meant to confirm these info.

Regards.
Alex Wong
User offline. Last seen 11 years 4 weeks ago. Offline
Joined: 12 Feb 2003
Posts: 874
Groups: TILOS
Sorry dont really understand your question.

"Can you justify this??" - Please explain a bit more

Alex
Nigel Hussey
User offline. Last seen 17 years 8 weeks ago. Offline
Joined: 28 Apr 2006
Posts: 31
Yes and no, depends on some settings. check your "Admin Preferences" on "Earned Value" calculations and also check "Resource Assignments" settings against your specific project.