Oracle Primavera - PM6 Member for 18 years 11 months Member for 19 years Submitted by Rama Krishnan on Sat, 2007-02-17 22:01 Permalink RE: Schedule % in P3e (Profiled) - Not tallying I took time off to study this Issue. I reviewed Primavera knowledgebase & found that they have an internal field called "Schedule Curve % Complete" But I do not see this field in my field selection list , say when I use the Columns selection in the activities window. Is there a way to get this displayed in my column for each activity? For ref. see Solution ID 20021220165416 Part 2)How is "Planned Value" calculated for activities with resource curves. BCWS="Scheduled Curve % Compl"*BAC Member for 22 years 8 months Member for 22 years 8 months Submitted by Alex Wong on Mon, 2006-11-06 19:57 Permalink RE: Schedule % in P3e (Profiled) - Not tallying Romo In that case please check your Plan Start Date and Plan finish date at the activity level If you dont mind, please send me the xer file and I can verify the project Alex Member for 18 years 11 months Member for 19 years Submitted by Rama Krishnan on Fri, 2006-11-03 07:48 Permalink RE: Schedule % in P3e (Profiled) - Not tallying Thanks Alex. I defined my resource as non-labour. I do update the following. Actual % manual update ( % Progress.-Physical), RDU Also I run a global change to calculate & update Actual resource qty & remaining qty based on % ( I have delinked automatic % vs. RDU). I am not sure what you mean by link actual to Project level? Thie Issue is getting the Plan % correct. "Schedule %" field displays correct value at WBS Band. But at Activity level it is still based on duration ie. Plan % = (Status date-BL Start)/(BL Finish - BL Start) Actually what I need is BL Resource Qty / BQ as a percent (Pick from curve) I could not search % rollup as some admin error in the forum regards, Rama Member for 22 years 8 months Member for 22 years 8 months Submitted by Alex Wong on Thu, 2006-11-02 20:22 Permalink RE: Schedule % in P3e (Profiled) - Not tallying Rama My question is Is your resource is Labor or Material or non material? When you progress your activity do you enter any actual value? Did you link your actual with progress in the project level? If you do a search on one of the topic call % rollup I had explain how P3e calculate physical progress and what are the rule of thrumb. Cheers Alex Log in or register to post comments
Member for 18 years 11 months Member for 19 years Submitted by Rama Krishnan on Sat, 2007-02-17 22:01 Permalink RE: Schedule % in P3e (Profiled) - Not tallying I took time off to study this Issue. I reviewed Primavera knowledgebase & found that they have an internal field called "Schedule Curve % Complete" But I do not see this field in my field selection list , say when I use the Columns selection in the activities window. Is there a way to get this displayed in my column for each activity? For ref. see Solution ID 20021220165416 Part 2)How is "Planned Value" calculated for activities with resource curves. BCWS="Scheduled Curve % Compl"*BAC
Member for 22 years 8 months Member for 22 years 8 months Submitted by Alex Wong on Mon, 2006-11-06 19:57 Permalink RE: Schedule % in P3e (Profiled) - Not tallying Romo In that case please check your Plan Start Date and Plan finish date at the activity level If you dont mind, please send me the xer file and I can verify the project Alex
Member for 18 years 11 months Member for 19 years Submitted by Rama Krishnan on Fri, 2006-11-03 07:48 Permalink RE: Schedule % in P3e (Profiled) - Not tallying Thanks Alex. I defined my resource as non-labour. I do update the following. Actual % manual update ( % Progress.-Physical), RDU Also I run a global change to calculate & update Actual resource qty & remaining qty based on % ( I have delinked automatic % vs. RDU). I am not sure what you mean by link actual to Project level? Thie Issue is getting the Plan % correct. "Schedule %" field displays correct value at WBS Band. But at Activity level it is still based on duration ie. Plan % = (Status date-BL Start)/(BL Finish - BL Start) Actually what I need is BL Resource Qty / BQ as a percent (Pick from curve) I could not search % rollup as some admin error in the forum regards, Rama
Member for 22 years 8 months Member for 22 years 8 months Submitted by Alex Wong on Thu, 2006-11-02 20:22 Permalink RE: Schedule % in P3e (Profiled) - Not tallying Rama My question is Is your resource is Labor or Material or non material? When you progress your activity do you enter any actual value? Did you link your actual with progress in the project level? If you do a search on one of the topic call % rollup I had explain how P3e calculate physical progress and what are the rule of thrumb. Cheers Alex
Member for
18 years 11 monthsRE: Schedule % in P3e (Profiled) - Not tallying
I took time off to study this Issue.
I reviewed Primavera knowledgebase & found that they have an internal field called "Schedule Curve % Complete"
But I do not see this field in my field selection list , say when I use the Columns selection in the activities window.
Is there a way to get this displayed in my column for each activity?
For ref. see Solution ID 20021220165416 Part 2)How is "Planned Value" calculated for activities with resource curves.
BCWS="Scheduled Curve % Compl"*BAC
Member for
22 years 8 monthsRE: Schedule % in P3e (Profiled) - Not tallying
Romo
In that case please check your Plan Start Date and Plan finish date at the activity level
If you dont mind, please send me the xer file and I can verify the project
Alex
Member for
18 years 11 monthsRE: Schedule % in P3e (Profiled) - Not tallying
Thanks Alex.
I defined my resource as non-labour.
I do update the following.
Actual % manual update ( % Progress.-Physical), RDU
Also I run a global change to calculate & update Actual resource qty & remaining qty based on % ( I have delinked automatic % vs. RDU).
I am not sure what you mean by link actual to Project level?
Thie Issue is getting the Plan % correct.
"Schedule %" field displays correct value at WBS Band. But at Activity level it is still based on duration ie.
Plan % = (Status date-BL Start)/(BL Finish - BL Start)
Actually what I need is BL Resource Qty / BQ as a percent (Pick from curve)
I could not search % rollup as some admin error in the forum
regards,
Rama
Member for
22 years 8 monthsRE: Schedule % in P3e (Profiled) - Not tallying
Rama
My question is
Is your resource is Labor or Material or non material?
When you progress your activity do you enter any actual value?
Did you link your actual with progress in the project level?
If you do a search on one of the topic call % rollup I had explain how P3e calculate physical progress and what are the rule of thrumb.
Cheers
Alex