Out of Sequence activities

Member for

19 years 11 months

keep it simple ... "Or just read the schedule log and hunt those activties down"

Member for

20 years 5 months

Kannan



You make a baseline, change the scheduling setting to ’progress override’ and then compare the finish date of the activties that are already started with the baseline dates. Populate a UDF saying "Out of Sequence" via global change and this will give you the ability to filter the activties.



Or just read the schedule log and hunt those activties down.



Regards

Rashid






Member for

19 years 11 months

using your subject ...



what is the diference between out of sequnece activities and activities with unsatisfied relationships?



regards.

Member for

19 years 11 months

Kannan,

Don’t think u can create a filter like this.

U have to schedule your project to see if there is any out of sequence activity.

Regards.