Hi Mr. David,



If I’m not mistaken, you can’t. "RA" is similar to "SDK" in P3. There is a Dictionary6x for P6. However, there is no WBS in here, only Activity Codes.



There is one more called "PATTLNK_632006_536-xerFileParser&Builder" but a little bit difficult to assign the WBS & Activity Code.



Regards,



Arnold

Member for

20 years 4 months

Can you use ’RA’ files in P5/P6?



If you can why don’t you export the WBS dictionery skeleton to the PROJECT.xls file, fill it out quickly in Excel and then re-import it?



David.

Member for

16 years 10 months

You are very correct. Thank you very much

Member for

18 years 6 months

Hi Alan,



Welcome to Planning Planet.



You can display the WBS & Activity Code in your Column and use the Fill down (CTRL+E). Or you can even drag/move the activities to the WBS level.



Another thing is, try to export to excel and assign it.



HTH.



Regards,



Arnold