Oracle Primavera - PM6 RE: Restoring A Baseline Go to "Projects" / "Baselines" highlight the baseline you want to see in "File Open" then hit the restore button. It will then be restored and visible as a standalone project. Regards, Ian RE: Restoring A Baseline Remember, U cant restore a baseline if it is defined as a Primary, Second or Third Baseline. Regards. RE: Restoring A Baseline Tim Davies Restoring a baseline, P3e creates a project with same name plus an increment in the same level of EPS of the project that u are restoring the baseline. Kind regards; Marcio Eduardo Rio de Janeiro - Brazil Log in or register to post comments
RE: Restoring A Baseline Go to "Projects" / "Baselines" highlight the baseline you want to see in "File Open" then hit the restore button. It will then be restored and visible as a standalone project. Regards, Ian
RE: Restoring A Baseline Remember, U cant restore a baseline if it is defined as a Primary, Second or Third Baseline. Regards.
RE: Restoring A Baseline Tim Davies Restoring a baseline, P3e creates a project with same name plus an increment in the same level of EPS of the project that u are restoring the baseline. Kind regards; Marcio Eduardo Rio de Janeiro - Brazil
RE: Restoring A Baseline
Go to "Projects" / "Baselines" highlight the baseline you want to see in "File Open" then hit the restore button.
It will then be restored and visible as a standalone project.
Regards,
Ian
RE: Restoring A Baseline
Remember,
U cant restore a baseline if it is defined as a Primary, Second or Third Baseline.
Regards.
RE: Restoring A Baseline
Tim Davies
Restoring a baseline, P3e creates a project with same name plus an increment in the same level of EPS of the project that u are restoring the baseline.
Kind regards;
Marcio Eduardo
Rio de Janeiro - Brazil