Restoring A Baseline

Member for

19 years 9 months
Permalink

Go to "Projects" / "Baselines" highlight the baseline you want to see in "File Open" then hit the restore button.



It will then be restored and visible as a standalone project.



Regards,



Ian

Member for

19 years 11 months
Permalink

Remember,



U cant restore a baseline if it is defined as a Primary, Second or Third Baseline.



Regards.

Member for

19 years 11 months
Permalink

Tim Davies



Restoring a baseline, P3e creates a project with same name plus an increment in the same level of EPS of the project that u are restoring the baseline.



Kind regards;



Marcio Eduardo

Rio de Janeiro - Brazil