Oracle Primavera - PM6 Member for 20 years 2 months Member for 20 years 2 months Submitted by MUHAMMAD IQBAL on Tue, 2005-11-15 05:05 Permalink RE: Add Resource Via Global Change hi guys why not u go to SQL and have Liberty to PLay with Primavera file this the most quickest way to deal with P3 data Member for 20 years 5 months Member for 20 years 6 months Submitted by Rashid Iqbal on Wed, 2005-08-03 10:03 Permalink RE: Add Resource Via Global Change Good one, it helped. Regards Rashid Member for 20 years 10 months Member for 20 years 10 months Submitted by Bill McMichael on Tue, 2005-08-02 21:41 Permalink RE: Add Resource Via Global Change You cannot do this through global change, but you can quickly assign multiple resources at once using assign resource dialog. Use filter to highlight the activities that meet your criteria. Not the same thing, but perhaps this will help. Regards, Bill Log in or register to post comments
Member for 20 years 2 months Member for 20 years 2 months Submitted by MUHAMMAD IQBAL on Tue, 2005-11-15 05:05 Permalink RE: Add Resource Via Global Change hi guys why not u go to SQL and have Liberty to PLay with Primavera file this the most quickest way to deal with P3 data
Member for 20 years 5 months Member for 20 years 6 months Submitted by Rashid Iqbal on Wed, 2005-08-03 10:03 Permalink RE: Add Resource Via Global Change Good one, it helped. Regards Rashid
Member for 20 years 10 months Member for 20 years 10 months Submitted by Bill McMichael on Tue, 2005-08-02 21:41 Permalink RE: Add Resource Via Global Change You cannot do this through global change, but you can quickly assign multiple resources at once using assign resource dialog. Use filter to highlight the activities that meet your criteria. Not the same thing, but perhaps this will help. Regards, Bill
Member for
20 years 2 monthsRE: Add Resource Via Global Change
hi guys
why not u go to SQL and have Liberty to PLay with Primavera file
this the most quickest way to deal with P3 data
Member for
20 years 5 monthsRE: Add Resource Via Global Change
Good one, it helped.
Regards
Rashid
Member for
20 years 10 monthsRE: Add Resource Via Global Change
You cannot do this through global change, but you can quickly assign multiple resources at once using assign resource dialog. Use filter to highlight the activities that meet your criteria. Not the same thing, but perhaps this will help.
Regards,
Bill