Copy & Paste between programmes

Member for

20 years 11 months

How very true. Given that I’m staff here, I really shouldn’t complain but.....

Member for

22 years 11 months

Incidentally, I’ve just copied activities in the activity view from one project to another without any trouble.



You do have permissions for both projects, dont you ?

Member for

22 years 11 months

No, it will copy all activities. Just delete those you dont want. Or in your source project segregate the activities you want into a temp wbs, copy to your target and then move source activities back to the original wbs.


Member for

20 years 11 months

Thanks Steven, does this work with partial sets of activities from the WBS?



Andy

Member for

22 years 11 months

Open both Source and Target, select Project, Wbs and copy your source wbs to target.





HTH