Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Resource Assignment Layout

2 replies [Last post]
Shahrol Sabaruddin
User offline. Last seen 13 years 2 weeks ago. Offline
Joined: 8 Feb 2005
Posts: 21
How to get only oustanding or in progress (Physical % Complete between 0% to 99%) Resource Assignment layout in P3e. I’m using P3e 3.5.1 by the way.

I’ve tried but it’ll will shows Resource Assignment with all activities including 100% complete. Could somebody help me.

Replies

Shahrol Sabaruddin
User offline. Last seen 13 years 2 weeks ago. Offline
Joined: 8 Feb 2005
Posts: 21
Thanks, Niek. It help!
Niek Zonneveld
User offline. Last seen 2 years 1 week ago. Offline
Joined: 17 Mar 2005
Posts: 188
Groups: None
Shahrol,

100% complete activities have an actual finish, so if you filter on: "actual finish equals [empty]" you’ll get what you are looking for.

Cheers,

Niek.