Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

START and FINSIH dates in P3E

7 replies [Last post]
Ali Hamouda
User offline. Last seen 7 years 49 weeks ago. Offline
Joined: 3 Feb 2002
Posts: 109
Groups: None
Hi,

I am new to P3e.

WHAT is the meaning of START AND FINISH DATES IN P3E.and why it is different from ES,EF & LS,LF as in P3.2.

and how the CPM is calculated? is it related with START AND FINISH.OR STILL RELATED TO ES,EF & LS,LF.

Replies

Luca Basile
User offline. Last seen 9 years 11 weeks ago. Offline
Joined: 10 Jul 2003
Posts: 288
Groups: TILOS
Yes, if you resource level the data will be from the leveling.
At difference from P3 3.1 these data will not change after a re-scheduling with the same data date.
Ronald Winter
User offline. Last seen 3 years 7 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None
The two fields, Planned versus Early dates, will be different if you are resource leveling and have the correct setting. Then Planned will have the resource-leveled dates and Early will have the CPM dates.
Luca Basile
User offline. Last seen 9 years 11 weeks ago. Offline
Joined: 10 Jul 2003
Posts: 288
Groups: TILOS
Raj I am agree with you in a CPM calculation.
Here we were discussing what P3e is showing in some fields.
The earliest dates is teh answer.

Cheers,
Luca
Raj Maurya
User offline. Last seen 2 years 43 weeks ago. Offline
Joined: 17 Jul 2004
Posts: 132
It will be early start & early finish if you are planning forward pass. In backward planning it will be late start and late finish.
Luca Basile
User offline. Last seen 9 years 11 weeks ago. Offline
Joined: 10 Jul 2003
Posts: 288
Groups: TILOS
The early date for both.


Luca


Ali Hamouda
User offline. Last seen 7 years 49 weeks ago. Offline
Joined: 3 Feb 2002
Posts: 109
Groups: None
your answer:

The START DATE, as per P3ec definition is the current start date of the activity. Set to the planned start date until the activity is not started, then to the actual.

what current value the start date will take if it s not yet started.is’t the Early start or the Late start?


and same question about FINISH DATE

thanks luca for your support.

Ali
========================================
Luca Basile
User offline. Last seen 9 years 11 weeks ago. Offline
Joined: 10 Jul 2003
Posts: 288
Groups: TILOS
Hi
The START DATE, as per P3ec definition is the current start date of the activity. Set to the planned start date until the activity is not started, then to the actual.
The FINISH DATE, as well is the completion date of the activity. Ste to the finish planned date till the activity is in the future, the remaining finish date till the activity is under progress, then the actual.

regards,
Luca

PS
In P3ec have been introduced the planned date, that may be user input with the aim to have another baseline.