Split activity bars in TeamPlay

4 replies [Last post]
Alexandre Faulx-B...
User offline. Last seen 18 hours 34 min ago. Offline
Joined: 20 Jan 2003
Content Credits: 1110
Hello,
Is it possible to split activity bars in the Primavera TeamPlay bar chart?
P3 knows the "neck" functionnality, but no "split".
Thanks

Replies

Paul Harris
User offline. Last seen 5 weeks 6 days ago. Offline
Alexandre

I am in the progress of updating my Primavera Version 3.5 book to Version 4.1 and I am discovering things on the way.

You will need to update to Primavera Version 4.1 which now has bar necking. It was not in 3.5 and I do not know about 4.0 but I suspect it was.

Just to clarify on splitting, the only splitting I have found in Primavera Version 4.1 is when Retained Logic or Actual Dates are used and then a task will split with Out of Sequence Progress.

Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Book Publishers, Training & Consulting
www.eh.com.au
mktse
User offline. Last seen 14 weeks 2 days ago. Offline
Joined: 27 Feb 2002
Content Credits: 524
I don’t think so.
As alternative (can apply on P3, not sure PEC), you can divide the bar into several segment. The ’split’ are will be in white colour and no boarder, so it look like ’disappear’ on print out, except the vertical sighe line still ’missing’ on the ’split’ area.
Alexandre Faulx-B...
User offline. Last seen 18 hours 34 min ago. Offline
Joined: 20 Jan 2003
Content Credits: 1110
Hi, Paul
it’s nice to work with someone staying the otherside of the globe!
I understand that P3 nor TeamPlay has the same functionnality as MS Project. My question is: does TeamPlay display the neck (in P3 the necked bar is slimmer) as a split?
All the best
Paul Harris
User offline. Last seen 5 weeks 6 days ago. Offline
Not in the way Microsoft Project does.

Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Book Publishers, Training & Consulting
www.eh.com.au

PP Market Place:
The XER Toolkit
: The toolkit provides advanced analytical tools which can help identify areas of poor schedule quality at the click of a button. (Software) Read more...