Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Workload

5 replies [Last post]
Rahmat Hidayat
User offline. Last seen 28 weeks 2 days ago. Offline
Joined: 30 Jul 2002
Posts: 82
Does anybody know how to create workload in P3e (like dia-in piping weld, m3 concrete pouring, M1 cable installation, ect).

I don’t understand why P3e v 3.51 categorize material as "expenses" (inderect cost), whereas there is many direct material that relevant with workload.

Replies

Alex Wong
User offline. Last seen 11 years 4 weeks ago. Offline
Joined: 12 Feb 2003
Posts: 874
Groups: TILOS
One way to measure the physical completion "Work Load" as you describe, is to use the combination of Physical completion and Steps in P3e. You set up the activty % type as Physical and then use the steps to identify the volumn of works is require for that particular activity. P3e will set up the weighting automatically. Once this activity is schedule you can progress it by updating the quantity in the Step. The % comp will be calculated automatically, since your resource and cost is already identified in the Resource you can link your cost with progress if desireable.
Rahmat Hidayat
User offline. Last seen 28 weeks 2 days ago. Offline
Joined: 30 Jul 2002
Posts: 82
Thank’s all for your responses.What I mean with workload is measurable work production by using a representative unit measurement. For instance, I want to measure piping work progress based on its welding production i.e. "dia-in. In this case unit price per "dia-in" already considered all associated resource costs (manpower, eqp, tool, consumable matl, and indirect portion). I hope this answer unclarity.

In my experience, we usually not control resources directly because we subcontract the works. Therefore we control the subcontractors based on their production.

As I know P3 v3.1 can do it but not in P3e v3.51.
Thks

No, it is not easy if you want to assign materials to a resource (gas to a car, electricity to a crane, etc.).

I understood the question differently, maybe the term workload was not used correctly, maybe I did not understood the question properly. I understood that Rahmat asked if you can assign materials to activities, basing on their quantitative characteristics, that was called workloads. We use this approach defining activity volumes in meters, tons or other physical units and then applying databases with the norms of material consumptions per one volume unit.

Maybe Rahmat will clarify his question?

Best Regards,
Vladimir
If I understood Rahmat correctly, workload and materials are not the same. For a certain length (100m for example) of the pipeline you will need 104 m of pipes (also an example) and a lot of other materials. Workload is the length, not materials that are necessary. We call it activity volume.
ming cheung
User offline. Last seen 19 years 45 weeks ago. Offline
Joined: 3 May 2004
Posts: 7
Groups: None
The best workaround is use the V4.0 release, which support materials as resource