Resource quantities can be negative in P3, so the short answer is yes.

 

You need separate activities, and you need to understand the payment calendar.  Is cash inflow about completeing milestones, or 30 days after an activity finishes? You can model it any way.

 

Graphics are harder as  P3 cannot go below zero on the "y" axis. Good old SureTrak let you do that.  IF you are a P3 shop, you might have a SureTrak licenece as well.......

Member for

21 years
Permalink

Resource quantities can be negative in P3, so the short answer is yes.

 

You need separate activities, and you need to understand the payment calendar.  Is cash inflow about completeing milestones, or 30 days after an activity finishes? You can model it any way.

 

Graphics are harder as  P3 cannot go below zero on the "y" axis. Good old SureTrak let you do that.  IF you are a P3 shop, you might have a SureTrak licenece as well.......