Critical Path - Graph like S-Curve

Member for

16 years 1 month

Hi Vishnu...sorry but the requeriment was ask to me bad...the people that ask it only need the S-curve but they have a wrong idea.



thanks

Member for

19 years 11 months

Hi Orozco,



I dont know if I understood your requirement correctly. Let me put it this way, - you need to have the critical activities one after the other arranged in terms of the early start/ finish dates.



This can be done by

1.Format - organize - Select activity data item - then remove all items under heading ’group by’

2.Under sort by - selct early start or early finish - order by ascend or descend



3. go to filter - and select the critical activities with the condition you have for the criticality (total float less than 5 or total float = 0 or whatever)



This will give you all critical activities listed one after the other.



I’m not sure whether this is what you are looking for.

Member for

16 years 11 months

Hi Orozco i am not sure about P3 but could do in a spreadsheet by selecting the activities respective durations followed by early dates .Generally this sort of procedure is called line of balance