Primavera Project Planner - P3 Member for 22 years 3 months Member for 22 years 3 months Submitted by Neeraj Agarkar on Sat, 2008-09-13 01:50 Permalink RE: How can I use Infomaker to customize the P3 report sorry for late response.. check under control panel - administrative tools - Data sources ODBC. you should not get error message once ODBC is set up. personally I prefer to use MSAccess or Excel than Infomaker. Regards Neeraj Log in or register to post comments
Member for 22 years 3 months Member for 22 years 3 months Submitted by Neeraj Agarkar on Sat, 2008-09-13 01:50 Permalink RE: How can I use Infomaker to customize the P3 report sorry for late response.. check under control panel - administrative tools - Data sources ODBC. you should not get error message once ODBC is set up. personally I prefer to use MSAccess or Excel than Infomaker. Regards Neeraj
Member for
22 years 3 monthsRE: How can I use Infomaker to customize the P3 report
sorry for late response..
check under control panel - administrative tools - Data sources ODBC. you should not get error message once ODBC is set up.
personally I prefer to use MSAccess or Excel than Infomaker.
Regards
Neeraj