Actual resources consumed

Member for

18 years 3 months
Permalink

you can record actuals in resource window, and store period performance



but im not sure if p3 reports can generate actual quantities graph and loading, only current and planned will be shown as far as i know



do it in excel

Member for

17 years 6 months
Permalink

Pinan,



Thanks for your reply.



Still my question is how do i enter data in P3 and generate tabular and graphical report.



Pipe fitter Mon - Fri 5*8= 40

Millwright Mon - Fri 5*8= 40



I am recoding progress every week and the reports to be submitted every Monday.



Appreciate help.



Salah

Member for

18 years 3 months
Permalink

get it from daily TIMESHEETS from ur Timekeeper..



Use Excel Charts for Comparison