Is there a way to undo Store Period Performance?

Member for

22 years 9 months

No, you can’t; if I remember well, you get a warning saying so when you click to store period performance

the only way to "remove" it is to backup your project schedule before doing it, and restore the schedule when you need it

Alexandre