Primavera Project Planner - P3 Member for 18 years Member for 18 years Submitted by gilbert gata on Thu, 2007-10-18 18:52 Permalink RE: Importing XER files to MPX Thanks Ronald, it works. Member for 22 years 9 months Member for 22 years 10 months Submitted by Ronald Winter on Tue, 2007-10-16 08:23 Permalink RE: Importing XER files to MPX Gilbert, Before you create your XER file, first open the schedule and run Administration / Purge Deletes. You XER file is probably full of unused information. Good luck! Member for 23 years 8 months Member for 23 years 8 months Submitted by MK TSE on Mon, 2007-10-15 18:59 Permalink RE: Importing XER files to MPX your topic and your content confuse me. 1. topic: import an XER (from P5.0) into MS Project The step is export P5 project into MS Project MPP format and open the MPP on MS project 2. content: import MPX to MS Project. It is not P5 related. Just open the MPX on MS project directly rather import btw, it is not P3 related, pleae post the question in "P3, P3e/c, Contractor" forum. Thanks in advance Log in or register to post comments
Member for 18 years Member for 18 years Submitted by gilbert gata on Thu, 2007-10-18 18:52 Permalink RE: Importing XER files to MPX Thanks Ronald, it works.
Member for 22 years 9 months Member for 22 years 10 months Submitted by Ronald Winter on Tue, 2007-10-16 08:23 Permalink RE: Importing XER files to MPX Gilbert, Before you create your XER file, first open the schedule and run Administration / Purge Deletes. You XER file is probably full of unused information. Good luck!
Member for 23 years 8 months Member for 23 years 8 months Submitted by MK TSE on Mon, 2007-10-15 18:59 Permalink RE: Importing XER files to MPX your topic and your content confuse me. 1. topic: import an XER (from P5.0) into MS Project The step is export P5 project into MS Project MPP format and open the MPP on MS project 2. content: import MPX to MS Project. It is not P5 related. Just open the MPX on MS project directly rather import btw, it is not P3 related, pleae post the question in "P3, P3e/c, Contractor" forum. Thanks in advance
Member for
18 yearsRE: Importing XER files to MPX
Thanks Ronald, it works.
Member for
22 years 9 monthsRE: Importing XER files to MPX
Gilbert,
Before you create your XER file, first open the schedule and run Administration / Purge Deletes. You XER file is probably full of unused information. Good luck!
Member for
23 years 8 monthsRE: Importing XER files to MPX
your topic and your content confuse me.
1. topic: import an XER (from P5.0) into MS Project
The step is export P5 project into MS Project MPP format and open the MPP on MS project
2. content: import MPX to MS Project.
It is not P5 related. Just open the MPX on MS project directly rather import
btw, it is not P3 related, pleae post the question in "P3, P3e/c, Contractor" forum. Thanks in advance