Tracking Activity Links

3 replies [Last post]
J Venkatesh PMP P...
User offline. Last seen 12 years 6 weeks ago. Offline
Joined: 7 Aug 2006
Posts: 52
Groups: GPC Qatar
Dear Planners,

I want to check/track the changes made in the activity links between the original and revised program...

The idea, am trying is exporting the predecessor / successor details of both the programs in to WK1 / Excel format and make a comparison check of the successor/predecessor columns of both the programs using excel functions..

but in reports, the precessor/suceessor can be viewed as Act Id*, Act Id* like that only...I mean, the predecessor/successor activity is shown with * mark only, not with the type of link and with the lag days...

Is there any option to see the links like Act Id SS+__ days, Act Id FS+ __ days (The link as per the program) the way we can see in MS Project..

Venkat

Replies

J Venkatesh PMP P...
User offline. Last seen 12 years 6 weeks ago. Offline
Joined: 7 Aug 2006
Posts: 52
Groups: GPC Qatar
Ronald and Dieter

Thanks a lot...

Venkat
Dieter Wambach
User offline. Last seen 8 years 9 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Hi Venkat,

if you look into the P3 example project, there is a prepared export EX12.

Or you create a new one: "ADD" --> enter the different criteria --> Under the detail tab "Content" select the radio button Successor relationship.

I hope, this will work

Dieter
Ronald Winter
User offline. Last seen 4 years 14 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None
Try "Tools / Project Utilities / Export" and check the "export successor relationships" radio button on the content page. Good luck!