Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

WBS and Hammock Activities

22 replies [Last post]
Brennan Westworth
User offline. Last seen 8 years 7 weeks ago. Offline
Joined: 23 Feb 2003
Posts: 150
Groups: None
Hi Planeteers,

I recently encountered a problem with P3 3.1.

I have a WBS activity summarising many hammocks and tasks. When a hammock activity is recorded as complete it seems to corrupt the WBS activity.

The early finish of the WBS activity runs out to project completion instead of being a summary of activities within that WBS level.

Has anyone encountered this before and have a suggested fix?

Cheers,
Brennan

Replies

Anoon Iimos
User offline. Last seen 3 years 23 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
try changing an updated (with actuals)WBS activity into a Hammock, Hammocks overrules actuals!

i don’t prefer to use Hammocks or WBS because you can never roll them up! therefore you cannot summarize them!
Santosh Bhat
User offline. Last seen 2 weeks 5 days ago. Offline
Joined: 15 Apr 2005
Posts: 381
WBS activities don’t summarise correctly if there is a hammock contained under that WBS level.
Alex Wong
User offline. Last seen 12 years 13 weeks ago. Offline
Joined: 12 Feb 2003
Posts: 874
Groups: TILOS
Hi Brennan

Long time no c
Try to answer your question, when a activity is marked with finished, all the effect of its successor logic is gone. As a result, if you only have one activity then your "Latest finish date" will become project completion date.

HTH

Alex
KongChung Chan
User offline. Last seen 10 years 24 weeks ago. Offline
Joined: 27 Jul 2004
Posts: 31
Groups: None
Brennan,

Fascinating issue. If you can send me the file please to chankc288-88@yahoo.com

Thanks
Carmen Arape
User offline. Last seen 7 years 44 weeks ago. Offline
Joined: 26 Jun 2004
Posts: 292
Hi Brennan,

Thanks for your answer. I got your E-mail and I will send the schedule in forthcoming days.

Give me some TIME, I am busy with JUN’07 Cut-off and I need to put the schedule in the same conditions when that happened. Do not forget that I did some tricks in oreder to get the proper late dates.

Thanks again & nice week

PS: Personally I do not like hammocks. I would rather work with codes for summarizing. Hammocks for me are the unwanted activities.
Brennan Westworth
User offline. Last seen 8 years 7 weeks ago. Offline
Joined: 23 Feb 2003
Posts: 150
Groups: None
Carmen, Your issue on Hammocks summarising float incorrectly is a bit off topic from WBS activities not summarising hammocks correctly, its probably worth creating a separate thread to work that one through. I would be interested in seeing a test schedule which replicates the problem you have described. Cheers, Brennan bwestworth@gmail.com
Brennan Westworth
User offline. Last seen 8 years 7 weeks ago. Offline
Joined: 23 Feb 2003
Posts: 150
Groups: None
Hi Ali,

I have forwarded you the test schedule.

Try adding another activity, outside of your WBS summary, which finnished later than the activities under your WBS summary.

You will find that your WBS activity runs out to the overall completion date, not the completion date of the activities it is suppose to be summarising.

Thanks for your assistance with this.
ALi Farahani
User offline. Last seen 1 year 16 weeks ago. Offline
Joined: 4 Jun 2007
Posts: 3
Hi Brennan ,

I read all your posts and created a test project & it seems to me that my project works well . my project has 9 activities , 3 task under 1 hammock & 2 task under another hammock & 1 task which is not under any hammock & 1 Wbs activity. all the activities have the same wbs code , i updated it and when the hammocks reach 100% , Wbs Activity works normal.

can u send your project to me , so i see what’s the problem & what’s the difference between my project & yours?
Carmen Arape
User offline. Last seen 7 years 44 weeks ago. Offline
Joined: 26 Jun 2004
Posts: 292
Hi All,

I was searching in all Forum the best “Forum Discussion Category” where I can place my question about Hammocks and I found your topic.

Although, my problem is not related to Hammock and roll up to WBS, I would like to forward my problem to the members to this discussion.

I have created some Hammocks for the purpose of allocating Man-hours and creating the man-hours distribution (based on early/late dates) using a trapezoidal curve.

I did it successfully but some hammocks did not show the proper late finish DATES according to the successors linked to Hammocks. I got some dates out of control.

My solution was to create Milestones with a mandatory finish DATE. I linked all the Hammocks to these Milestones so that the backward calculation of dates (late dates) was done correctly.

Does anyone have experienced same problem.

Looking forward any comment.

carmen
Anoon Iimos
User offline. Last seen 3 years 23 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
sorry, (maybe I just don’t understand it); but I’ve tried once using rolled-up with costs inputs and it works fine. I think it’s just a matter of organization, which you don’t have to conflict as one function might drive the other.

I think i’m not qualified to help you, I believe there were lots of authorized persons ’round here..

cheers
Brennan Westworth
User offline. Last seen 8 years 7 weeks ago. Offline
Joined: 23 Feb 2003
Posts: 150
Groups: None
The reason I use summary activities instead of rolled up summaries is because I need to record activity data (earned value and actual cost) at a higher level than my detailed schedule.

Anoon Iimos
User offline. Last seen 3 years 23 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
i suggest that you use rolled-up activities, but some are saying that it does’nt work in calculating exact Free Floats and Total Floats; i just don’t have the time to find it myself
Anoon Iimos
User offline. Last seen 3 years 23 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
you know what? I maybe stupid! but I suppose I’ll never use that kind of presentation; Why?; I think it’s conflicting, you got three (3) driving functions! WBS; Hammocks; and Tasks! and it would be very difficult to organize (at least from my experience). Why not try using Activity Codes? i’m not sure,.. you know better that I...

cheers
Anoon Iimos
User offline. Last seen 3 years 23 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
I have to admit that it’s the first time for me to see that kind of demostration/presentation (Test Project that you sent). I’m not professionally trained in P3, I just learned it by chance by myself. I usually worked on Activity Codes...but give me time and let me try!

cheers
Brennan Westworth
User offline. Last seen 8 years 7 weeks ago. Offline
Joined: 23 Feb 2003
Posts: 150
Groups: None
I hope that test file I emailed you demonstrates the problem clearly.
Anoon Iimos
User offline. Last seen 3 years 23 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
if you got spare one for me in Australia, then why not?

i can find out what exactly your problem is (if you don’t mind)
Brennan Westworth
User offline. Last seen 8 years 7 weeks ago. Offline
Joined: 23 Feb 2003
Posts: 150
Groups: None
P3 has two summary activity types
- Hammock, which uses logic to summarise
- WBS, which uses WBS Code to summarise

I was using Hammock summary activities within a WBS summary activity and P3 couldnt handle it.


By the way... is there much work going on in Antarctia? :)
Anoon Iimos
User offline. Last seen 3 years 23 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
i don’t understand what you mean exactly, but I guess you’re referring to Activity Codes or coded activities against WBS..you can always roll-up activities to represent a summary but Hammock I guess has different function, it also summarises activities but in a different way I guess.
Brennan Westworth
User offline. Last seen 8 years 7 weeks ago. Offline
Joined: 23 Feb 2003
Posts: 150
Groups: None
I just created a simple test schedule.

it seems that you can only have WBS OR Hammock activities.
Brennan Westworth
User offline. Last seen 8 years 7 weeks ago. Offline
Joined: 23 Feb 2003
Posts: 150
Groups: None
the only thing I can think of is to abandon WBS activities all together and convert them to hammocks.
Brennan Westworth
User offline. Last seen 8 years 7 weeks ago. Offline
Joined: 23 Feb 2003
Posts: 150
Groups: None
The hammocks are summarising fine, the problem occurs when a hammock activity, within a WBS level, reaches 100% complete.
Anoon Iimos
User offline. Last seen 3 years 23 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
haven’t encountered actually, but P3’s definition of Hammocks is that: it is to have one predecessor and one successor to define or drive its duration; I guess if the last activity in your WBS ends with the completion date and also serve as the successor activity to your Hammock, then I guess that’s where the problem occurs. (but i’m not sure)