Update Progress P3 3.1

Member for

22 years 5 months

Dear Paul,

When you do automatic update, then P3 assume that everything are moving as per plan and update every activity as per initial base plan. If there are any deviations then update as mentioned by Arvin and Anoon.

Regards

Member for

19 years 1 month

some people are claiming that P3 is becoming obsolete while others still don’t have a clue! (including me);



P3 is using Duration; Resource Units and Costs



in updating P3 by just putting actuals, make sure you chose Duration



when you’re using Resources Units (which i supposed seldom used or never), make sure you got all the quantities!



when using Cost! I’m sure you’ll never get what you want!

Member for

22 years 4 months

Agree with Arvin.. if you’re updating your program just put all the actuals and press F9..

Member for

18 years 5 months

Because



Update progress is an automatic way of updating a project. Meaning P3 quickly estimates activity dates, percent complete amounts, and remaining durations as of the new data date you specified by dragging the data-date line or by using the Progress Spotlight feature.