Adding Ramzan (Hourly) calender into P3

Member for

18 years 5 months

Hi Alex,



You are very correct if the total duration is in weeks then we should plan in hours e.g.shutdowns etc.





Regards,



Ashraf

Member for

22 years 9 months

ashraf,

for sure planing the project in hours instead of days would be more simple, but it does not sound logical for every one to plan a 30 month project in hours, don’t you agree?

bqa 3ala kheir

Alexandre

Member for

18 years 5 months

Thanks Ashraf for the immediate response given.



This doesn’t work, but yaa as alex said i have to show every alternate day in ramdan month as non-working, which is not correct logically, but thats the only solution.



Cheers,



Raviraj

Member for

18 years 5 months

Hi Alex/Ravi,



Have you tried copying this project with HOURS as planning unit. I hope if it works the solution will be much simple.





Regards,



Ashraf

Member for

22 years 9 months

Hi Ravi & Ashraf,

I have just given the same advice to one customer in Algeria: create a "Ramadhan" daily calendar where every other day is a nonworking day.

You can only create calendars with the same unit as the project planning unit.

mâa salama

Alexandre

Member for

18 years 5 months

Hi Ravi,



The answer to your question is NO you cannot add one more calender as planning Unit - HOUR, when you have already allocated calender with planning unit as DAY.





You can try making a Calendar with equivalent working days (3 instead of 6). This may help to some extent.



Regards,



Ashraf