Just now I have seen your question, it seems to be an old posting, anyhow let me try to answer your question.
you can display the resources quantities for an activity in resource table. to do this, click Resource/Cost Table icon from the menu, then click select button, choose the three resources one by one under the "Low Value Resource". Thats it. you can see the resources quantities against each resources in the table(Note if your activities are overlapped, you will get summarized quantity for the resource in any specific day/week/month)
Can you be a little more specific in steps? If you have, say, three types of resources, when you get budgeted quantity, P3 gives you the total quantity of all the three resources. What you want is quantity of each resource separately.
RE: Showing resource units in table
Just now I have seen your question, it seems to be an old posting, anyhow let me try to answer your question.
you can display the resources quantities for an activity in resource table. to do this, click Resource/Cost Table icon from the menu, then click select button, choose the three resources one by one under the "Low Value Resource". Thats it. you can see the resources quantities against each resources in the table(Note if your activities are overlapped, you will get summarized quantity for the resource in any specific day/week/month)
HTH
RE: Showing resource units in table
Christian,
Can you be a little more specific in steps? If you have, say, three types of resources, when you get budgeted quantity, P3 gives you the total quantity of all the three resources. What you want is quantity of each resource separately.
RE: Showing resource units in table
Hello Bijaya
What you can do is create a layout for your resources then label your bars with their corresponding quantities..
HTH
Christian