What I normally do is to save a copy of the levelled schedule as a target schedule for later reference.
In addition, the reason that you don’t really need to keep the schedule becasue each time the senario changes you will need to re-level your schedule base on the new conditions. What you however need to save is your levelling setup.
Priority, Float control...
HTH
Alex
Member for
20 years 6 months
Member for20 years6 months
Submitted by Zhang Haixiang on Wed, 2005-11-09 20:57
I agree with Ronald. Creat a custon data item to store leveled date for reference.
and be careful using constraints. After updating your schedule, youd better re-schedule and re-leveling, because critical path/total float/free float may change, the result of leveling will also change.
Member for
22 years 9 months
Member for22 years10 months
Submitted by Ronald Winter on Wed, 2005-11-09 10:56
It is easy to remember scenarios. Create Custom Data Fields for the Early Dates and then use global edit to transfer the leveled dates into this new field. Done! Good luck.
Member for
22 years 11 months
Member for23 years
Submitted by Hemanth Kumar on Wed, 2005-11-09 05:47
Member for
22 years 8 monthsRE: levelling of resources
Echo.......................
Back to the original question
What I normally do is to save a copy of the levelled schedule as a target schedule for later reference.
In addition, the reason that you don’t really need to keep the schedule becasue each time the senario changes you will need to re-level your schedule base on the new conditions. What you however need to save is your levelling setup.
Priority, Float control...
HTH
Alex
Member for
20 years 6 monthsRE: levelling of resources
Sunil,
I agree with Ronald. Creat a custon data item to store leveled date for reference.
and be careful using constraints. After updating your schedule, youd better re-schedule and re-leveling, because critical path/total float/free float may change, the result of leveling will also change.
Member for
22 years 9 monthsRE: levelling of resources
It is easy to remember scenarios. Create Custom Data Fields for the Early Dates and then use global edit to transfer the leveled dates into this new field. Done! Good luck.
Member for
22 years 11 monthsRE: levelling of resources
Not Possible My Friend
Levelling gives scenarios
if you want to retain dates note it down and constrain activities