levelling of resources

Member for

22 years 8 months

Echo.......................



Back to the original question



What I normally do is to save a copy of the levelled schedule as a target schedule for later reference.



In addition, the reason that you don’t really need to keep the schedule becasue each time the senario changes you will need to re-level your schedule base on the new conditions. What you however need to save is your levelling setup.

Priority, Float control...



HTH



Alex

Member for

20 years 6 months

Sunil,



I agree with Ronald. Creat a custon data item to store leveled date for reference.



and be careful using constraints. After updating your schedule, you’d better re-schedule and re-leveling, because critical path/total float/free float may change, the result of leveling will also change.

Member for

22 years 9 months

It is easy to remember scenarios. Create Custom Data Fields for the Early Dates and then use global edit to transfer the leveled dates into this new field. Done! Good luck.

Member for

22 years 11 months

Not Possible My Friend

Levelling gives scenarios

if you want to retain dates note it down and constrain activities