Forum Sponsor:

An innovation in P6 Professional training from RPCuk in partnership with Oracle. All the topics that matter to you in workshops customised to your role and industry.  Now get superior training value when you book our Blended Learning Bundle. Learn more here.

Viewer for .xer, xml and xls schedule files Schedule Reader™Free Trial

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Splitting Activities - Error Reason 46

1 reply [Last post]
Mark Docherty
User offline. Last seen 13 years 49 weeks ago. Offline
Joined: 27 Jan 2005
Posts: 3
Groups: None
I am a relatively new user of P3 and i’m experiencing problems showing multiple bars against one activity.

I have tried splitting the activity via the Levelling Field but when i run this an error message comes up as follows - ’Could not get a lock on multiuser record, reason = 46. Sort/Select Completed, problem encountered.

Any advice would be much appreciated.

Replies

Alex Wong
User offline. Last seen 6 years 30 weeks ago. Offline
Joined: 12 Feb 2003
Posts: 874
Groups: TILOS
Have you try exclusive access to the project??

When you open a projects you have a option to open it exclusively.

HTH