What I am suggesting is really to put these expected finish dates only on activities that have an actual start, meaning that I have a strong reference to foresee their finish dates.
It prevents me to be obliged to bring back their end dates after moving the data date. When you have large quantities of activities to update every week, I still believe that this could ease the planner job.
Member for
20 years 3 monthsRE: Resource Percent Complete
Yes I use Primavera 3.1
What I am suggesting is really to put these expected finish dates only on activities that have an actual start, meaning that I have a strong reference to foresee their finish dates.
It prevents me to be obliged to bring back their end dates after moving the data date. When you have large quantities of activities to update every week, I still believe that this could ease the planner job.
I hope I will find some supporters!
;-)
YVes
Member for
20 years 3 monthsRE: Resource Percent Complete
Use RPCT equals PCT
Yves Trudel