Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Resource Percent Complete

3 replies [Last post]
Amar Aghana
User offline. Last seen 16 years 37 weeks ago. Offline
Joined: 15 Aug 2005
Posts: 103
Hi Guys,

I want to run a global change to show Resource Percent Complete (RCP) equal to Percent Complete(PCT)

1) How to create a global change command for this.

I tried RCP EQ PCT

RCP is not a correct command.

2) By entering Resource Percent Complete (RCP)also while updating, I hope we will be projecting resource requirement correctly for the balance period.

Please advise.

Replies

Yves Trudel
User offline. Last seen 17 years 16 weeks ago. Offline
Joined: 30 Jul 2005
Posts: 33
Groups: None
Yes I use Primavera 3.1
What I am suggesting is really to put these expected finish dates only on activities that have an actual start, meaning that I have a strong reference to foresee their finish dates.
It prevents me to be obliged to bring back their end dates after moving the data date. When you have large quantities of activities to update every week, I still believe that this could ease the planner job.
I hope I will find some supporters!
;-)
YVes
Bill Guthrie
User offline. Last seen 7 years 50 weeks ago. Offline
Joined: 14 Mar 2005
Posts: 262
check your autocost rules set up

bill
Yves Trudel
User offline. Last seen 17 years 16 weeks ago. Offline
Joined: 30 Jul 2005
Posts: 33
Groups: None
Use RPCT equals PCT
Yves Trudel