I have the same kind of problem.

In my project schedule, when they created, entered the resources (manhour, = BQ*productivity) and BQ in the resources itself. They have given different names for the resources and differrent names for BQ also. I want to a show seperate column to show the resource name, manhour and the same for BQ also. Experts please in details as I am not much familier with p3.



Thanks

Member for

20 years 5 months

Hi Onur,

In order to get Resource Dictionary and Resource Unit Prices in excel format I suggest you to use project.xls (you can find it in P3 cd-rom \Support\UTILS\EXCEL\).



Regards

Giannis

Member for

20 years 4 months

Hi,

i already send the ammended formula, u can use straight away, or u can send me your file i can repair it for u.

Member for

20 years 2 months

Hi Raja,



Price per unit in our project is not Budgeted Cost divided by original duration . In our project although i changed the original duration our resource price per unit keeps its original value what we wrote before in the res.dictionary .



I want the values in the resource dictionary



Thanks

Member for

20 years 4 months

Hi

create a column....suggest use global change? I hope u fimiliar with global change... so i dont have to explain detail. Any how if needed...no problem. Just ask