Primavera Project Planner - P3 Member for 20 years 7 months Member for 20 years 8 months Submitted by Sukumaran Suba… on Mon, 2005-05-30 06:19 Permalink RE: graph Hi Jarka, Do you mean S-Curve and Histogram? If yes, go to Tools > Graphic Reports > Resource and Cost. There are few built in graphs. You can go through it and find out the information you are required. Regards. Log in or register to post comments
Member for 20 years 7 months Member for 20 years 8 months Submitted by Sukumaran Suba… on Mon, 2005-05-30 06:19 Permalink RE: graph Hi Jarka, Do you mean S-Curve and Histogram? If yes, go to Tools > Graphic Reports > Resource and Cost. There are few built in graphs. You can go through it and find out the information you are required. Regards.
Member for
20 years 7 monthsRE: graph
Hi Jarka,
Do you mean S-Curve and Histogram? If yes, go to Tools > Graphic Reports > Resource and Cost. There are few built in graphs. You can go through it and find out the information you are required.