Store Period Performance

Member for

17 years 5 months

Dear Alex,



Thank you for your notice. I was talking about P3.



Regards,



Safak

Member for

22 years 8 months

FYI



If it is P6 you talking about, you can edit your stored PP provided you have the access right



HTH



Regards



Alex



(I use PP to predict the project end date and the 20/80 rule work pretty good)

Member for

16 years 2 months

Hi Safak,

Thank you a lot for your valuable reply.



I will do the export-import solution and post back the result.



Regards,

Mohammad

Member for

17 years 5 months

Hi Mohhammed,



There is no way to undo stored values in a project. But if you have to undo then i can suggest you to create a new schedule and export-import all data and relations from existing schedule.



Store period performance should be a must if you have an opportunity for a forensic analyses. A good resource loaded and tracked schedule could show what-how the works done months ago with just a few clicks.



The worst nightmare about store perion performance is being seen if you are changing budgets, durations of activities while revising or re-forcaasting schedule. You will have variances and you will need rewrite some resource values or global change a few times to clear the variances. I also encounter import-export problems for percentage completes in P3.



As conclusion it is not a must but it is a should. It isnt must due to : "The best schedule is the schedule you can manage".



Regards,



Safak

Member for

16 years 2 months

Hi All,

Can you please advice if I can undo this option? Someone have done it on our project (Primavera 6 installed) and we are not aware of how we can remove it now !



Thanks in advance for your help





AJ

Member for

22 years 3 months

RA (SDK)? Sounds new to me. Would you mind to elaborate further.

Member for

22 years 7 months

you can use P3 Ra (SDK) application to study the things and implement accordingly as per your requirements, anyhow it will take sometime.

Member for

22 years 3 months

If the Stored Period Performance of a certain schedule is done quarterly and let us say we want to switch to store our schedule in monthly or weekly, is there any short way to update considering an available data in spreadsheet. Does "Import" tools is applicable?

Member for

22 years 8 months

In order to overcome the 0 actual / unit problem I usually run a global change that impose any resource that had a 0 this period with a $0.1 prior to store period performance, that way it is always correct

Member for

22 years 7 months

sure u can continuously update and store period performance in the same p3 file (for each monthly update). But it is useful if you maintain p3 files separately such ud01, ud02, ud03 for each monthly update. It would be meaningful(filemaintenance) to supply the files to client, u can check for any slippage in time as compared to previous monthly update by keeping ud03 as target for updating progress in ud04, also useful for preparation of disruption analysis as and when required.

Member for

22 years 6 months

If i’ve stored the period performance of activity (say ud01..file)again next time same file i can update.if not then why?

Member for

22 years 7 months

Dear Ali,



The following procedure will show you the importance of store period performance.



Let us say each monthly update shall be denoted as ud01 (jan), ud02(feb), ud03(mar) for ideal cases.........



Assume some 50 number of foundations in a design unit, you are respresenting it as an activity and loaded with a resource called BQFdn and assigning 50 in Budgeted Quantity.



Assume some foundation works commenced in Feb, say 10 no of foundations completed before the status date of ud02. you update this status in actual to date field by entering 10 and schedule the program. in the next update say ud03(you have to copy ud02 as ud03 first), before statusing the activity(or any activities) you must store the period performance option in ud03 file, then you can notice the actual this period field will show 0 for the foundation activity, which means the number of 10 foundations completed in the previous month has been stored in the database, and ready for fresh-update to display the progress in march(ud03 update), then start to status the activity say another 20 foundations completed, enter the actual to date as 30 and schedule the project(remember again you should not press the store period performance)in ud03 file. so that you can see the historical actual number of foundations completed when you run the s-curve as well early finish date for remaining foundations will be shown in the s-curve.



of course our fellow planners clearly explained about EV............ if you still have some doubt you can use any google search engine to search for EVM concepts.........



hope the above will clarify the importance of store period performance.

Member for

22 years 8 months

EV stand for Earn Value

The progress of work converted to a $ value

ie if the project is budgeted to $10

and if you finished 30% of the job the eared value will be $3

How it help you to track and plan your job

ie if this project is spread over 3 days



after day 1 the project is 30% complete and you spend $5 dollar and day 2 you spend additional $3 and remaining at 30% complete. If you save your period performance every day with P3. you can then plot your ev curve as well as you actual dollar curve and with the data you can then forecast the furture. However, if you do not save the period performance then what happen is you will always have the average of all the past data that means you curve will show day 1 you spend $4 and same as day 2 and you earn $1.5 per days as well. However, this is a misleading information since day 2 you spend $3 and earned $0 if the period is longer than you will see the different.


Member for

16 years 9 months

I still don’t understand the function of Store Performance Period.

What is EV?

How’s it help for monitoring purpose?

Can you explain in more detail and simple?



Ali Ham.

Member for

22 years 3 months

I had always problems with store period performance, in particular way in big schedule.

I prefer to prepare all the graphs in excel (c-curves, etc ...).

Member for

16 years 9 months

Store Period Performance function store the actual (Both resource and cost) to a file in the P3 database.



If this is applied for every report period. Then you can have see actual resource/cost usage over time. A better audit trail.



Without it, P3 will spread the resource / cost data linearly between the activity start and finish date only.



Hence you can not see the actual usage overtime.

Member for

21 years 6 months

It’s an option.



Store period performance will store the EV (quantity & cost) for the datadate you store it on. If you don’t do that, P3 will level out the EV on each task.



Example:



Task takes 10 days with a BQ of 100. After day 5, you are 50%. This means that you have an EV of 10 per day. If you are still 50% after 10 days, you will have a EV of 5 per day! That means that the historic date from the first 5 days will be spread over the 10 days that the task is in progress and thus your progress line will drop in the S-Curve.

If you store period performance, the EV of 50 will remain on the 5 days and the other 5 days that you didn’t earn anything will have a EV of 0 (zero). Your progress line will show the EV of 50 in the first 5 days and a horizontal line the next 5 days.



Hope this is clear enough.