Dear All,
I want to show the suspension of activity four times due to obstructions. as we are using P3 please tell me a way to show this in a program its single activity (placing conduite)
I am agree with Choi, is not that You have to put several suspension and resume because Your schedule is to high level?
If not split down it in any case in different activities, put before a milestone with an "self explaning" start milestone taht will help You later on in the possible preparation of the claim.
To group the activities resulting from this splitting use the coding structure.
When You just put suspend and resume you loose the reason, I prefer to split and put self explaining milestone.
I believe your down times should have reasons for that.
Options:
1. sub-divide your activity into avtivities.
2. create a new calendar and assign the down time as non-working dates in the calendar.
Hope this will help.
RE: Suspension Dates on P3
Go to Bars and make sure NECK is under visible mode.
If neck is unchecked, then it will show a straight bar.
Cheers,
Rav
RE: Suspension Dates on P3
Hi Rav
I followed your steps but no changes in the bar how does it appears????? will version 5 helps ....
GA
RE: Suspension Dates on P3
you can show suspended activities by pressing F7 --> DATES Tab --> Suspend date and resume date
We cannot show suspension activities in baseline program. In updated program, it must have actual date.
But, activity suspension for four times......? I dont think so, its possible in P3. You can show it only once, I believe.
Cheers,
Rav
RE: Suspension Dates on P3
Dear All,
I want to show the suspension of activity four times due to obstructions. as we are using P3 please tell me a way to show this in a program its single activity (placing conduite)
GA
RE: Suspension Dates on P3
tx alot guys and best regards....
ALFON
SCDC
RE: Suspension Dates on P3
I am agree with Choi, is not that You have to put several suspension and resume because Your schedule is to high level?
If not split down it in any case in different activities, put before a milestone with an "self explaning" start milestone taht will help You later on in the possible preparation of the claim.
To group the activities resulting from this splitting use the coding structure.
When You just put suspend and resume you loose the reason, I prefer to split and put self explaining milestone.
RE: Suspension Dates on P3
You should be seperately recording each and every occasion where for no fault of your own you are unable to proceed.
This gives a full record of interruptions to the work and is invaluable if you needed to prepare a claim.
RE: Suspension Dates on P3
I believe your down times should have reasons for that.
Options:
1. sub-divide your activity into avtivities.
2. create a new calendar and assign the down time as non-working dates in the calendar.
Hope this will help.