Late finish dates are set by the backward pass of the schedule
for the total project late dates 1st it looks for a Project must finish by date then calculates backwards in time from that date taking into the logic and durations and determines the LATEST and activity can finish and start without delaying the project.
it would also look for an activity with finish on or before constraint on it and also calculate backwards in time from that date to determine the late dates
if there is NOT a project must finish by date set or a finish on or before constraint on the last logical activity in the schedule then the late finish date WILL EQUAL THE EARLY FINISH DATE because it has no where else to start to calculate the backward pass
Late Dates are derived from the backward pass starting at the projetc must finish by date
Early dates are derived from the forward pass starting at the date date or the start date of the project
The difference between the early and date date is the total float
I have a related question,.....I am getting a message when I try to reduce the Remaining Duration, the message is "Remaining Finish can not be less then Remaining Start".
I am guessing this is talking about the Late Finish Date or maybe the Planned Finish Date? either way, the reduced duration that I want to enter is correct, the Expected Finish Date that I want is Correct, so how do I clear the fields that are generating this message?
I have a related question,.....I am getting a message when I try to reduce the Remaining Duration, the message is "Remaining Finish can not be less then Remaining Start".
I am guessing this is talking about the Late Finish Date or maybe the Planned Finish Date? either way, the reduced duration that I want to enter is correct, the Expected Finish Date that I want is Correct, so how do I clear the fields that are generating this message?
when I start to schedule the project the Late finish should be the same as the Base plan(or the Target),if we adjust the Autocost rules to calculate the total float on the late finish.
some times it happen that the Late finish changed.
inspite that it should be the same as the Target.
I am not sure exactly what is the reason.
But I am sure that the Late finish of the project should not change, because this is our limit,and according to that the T.F is calculated.
Best Regards
Member for
23 years 8 months
Member for23 years9 months
Submitted by Colin Cropley on Fri, 2002-03-22 12:10
Late Finish, as for late start and early start and finish, is calculated by the scheduling software.
You can set the late finish by use of certain constraints:
1. Set a Finish No Later than constraint. this will only override the calculated date if it is earlier than the calculated date.
2. Set a Zero Total Float constraint. This sets the late dates equal to the early dates (usually used to make open ended paths critical).
3. You might be able to set the late finish by setting an Expected Finish constraint, plus a Zero Total Float constraint, but I am not sure why you would do this and I haven't tried it. This will also set the Early Finish as well.
Member for
21 years 7 months(No subject)
Member for
16 years 3 monthsLate finish dates are set by
Late finish dates are set by the backward pass of the schedule
for the total project late dates 1st it looks for a Project must finish by date then calculates backwards in time from that date taking into the logic and durations and determines the LATEST and activity can finish and start without delaying the project.
it would also look for an activity with finish on or before constraint on it and also calculate backwards in time from that date to determine the late dates
if there is NOT a project must finish by date set or a finish on or before constraint on the last logical activity in the schedule then the late finish date WILL EQUAL THE EARLY FINISH DATE because it has no where else to start to calculate the backward pass
Late Dates are derived from the backward pass starting at the projetc must finish by date
Early dates are derived from the forward pass starting at the date date or the start date of the project
The difference between the early and date date is the total float
Member for
13 years 4 monthsI have a related
I have a related question,.....I am getting a message when I try to reduce the Remaining Duration, the message is "Remaining Finish can not be less then Remaining Start".
I am guessing this is talking about the Late Finish Date or maybe the Planned Finish Date? either way, the reduced duration that I want to enter is correct, the Expected Finish Date that I want is Correct, so how do I clear the fields that are generating this message?
Rod
Member for
13 years 4 monthsI have a related
I have a related question,.....I am getting a message when I try to reduce the Remaining Duration, the message is "Remaining Finish can not be less then Remaining Start".
I am guessing this is talking about the Late Finish Date or maybe the Planned Finish Date? either way, the reduced duration that I want to enter is correct, the Expected Finish Date that I want is Correct, so how do I clear the fields that are generating this message?
Rod
Member for
23 years 8 monthsRe: Late Finish Change.
Hello Mr.Collen,
Actually the problem that I met was:
when I start to schedule the project the Late finish should be the same as the Base plan(or the Target),if we adjust the Autocost rules to calculate the total float on the late finish.
some times it happen that the Late finish changed.
inspite that it should be the same as the Target.
I am not sure exactly what is the reason.
But I am sure that the Late finish of the project should not change, because this is our limit,and according to that the T.F is calculated.
Best Regards
Member for
23 years 8 monthsRe: Late Finish Change.
Late Finish, as for late start and early start and finish, is calculated by the scheduling software.
You can set the late finish by use of certain constraints:
1. Set a Finish No Later than constraint. this will only override the calculated date if it is earlier than the calculated date.
2. Set a Zero Total Float constraint. This sets the late dates equal to the early dates (usually used to make open ended paths critical).
3. You might be able to set the late finish by setting an Expected Finish constraint, plus a Zero Total Float constraint, but I am not sure why you would do this and I haven't tried it. This will also set the Early Finish as well.