Tasks dates not imported in P6

Member for

9 years 8 months

Rox,

 

P6’s main purpose is to calculate start and finish dates.  Specifically Early, remaining early, late, remaining late and planned start and finish. It is a long time since I imported an MPX file, but when importing a spreadsheet you cannot import any of these dates, you can only import dates that are input to the schedule calculations.  To populate date fields in P6 you need to schedule.