P6’s main purpose is to calculate start and finish dates. Specifically Early, remaining early, late, remaining late and planned start and finish. It is a long time since I imported an MPX file, but when importing a spreadsheet you cannot import any of these dates, you can only import dates that are input to the schedule calculations. To populate date fields in P6 you need to schedule.
Member for
9 years 8 monthsRox, P6’s main purpose is to
Rox,
P6’s main purpose is to calculate start and finish dates. Specifically Early, remaining early, late, remaining late and planned start and finish. It is a long time since I imported an MPX file, but when importing a spreadsheet you cannot import any of these dates, you can only import dates that are input to the schedule calculations. To populate date fields in P6 you need to schedule.