For a granular view I like to display Gantt showing for every activity the volume of work, the resource assignments, materials consumption and production rates.
hoover image click and then zoom.
Member for
21 years 7 months
Member for21 years8 months
Submitted by Rafael Davila on Tue, 2022-11-29 13:13
Member for
21 years 7 monthsFor a granular view I like to
For a granular view I like to display Gantt showing for every activity the volume of work, the resource assignments, materials consumption and production rates.
hoover image click and then zoom.
Member for
21 years 7 monthsI would show maximum weekly
I would show maximum weekly quantities for all resources in a single table.