Non Labor Units Changes

Member for

10 years 6 months

Thanks,
This method solved the issue.

Member for

19 years

Hi Siddiq,

It seems that the Calculation Settings on your resource assignment is link to duration %.

1) Goto Project module or click the folder icon (Project) on the left of your screen.

2) Click the project that you are updating (you will see that the folder icon for this project is open)

3) Select or click the Calculation Tab

4) Under the Resource Assigments (right side of the tab) Untick the box with "Recalculate Actual Units and Cost when duration % complete changes.

5) Then go back to Activity module and change the actual unit then re-calculate (F9). Check if the Actual units still changing after re-calculate or run schedule.

I hope this solve your problem.