your scheduled % complete is from your basline schedule it is the total planned mahours for the project divided by the cumulatived manhours up to that month
i.e. total planned manhours 100
total cumulative manhours at the end of that month = 10
Hi, I have manhours assigned to each activity, what I'm trying to get in spreadsheet is literally Schedule % Complete, not budgeted units or remaining units or BL budgeted units.
Member for
16 years 3 months
Member for16 years3 months
Submitted by Zoltan Palffy on Mon, 2019-11-18 14:29
Member for
16 years 3 monthsyour scheduled % complete is
your scheduled % complete is from your basline schedule it is the total planned mahours for the project divided by the cumulatived manhours up to that month
i.e. total planned manhours 100
total cumulative manhours at the end of that month = 10
therefore 100/10= planned 10% complete
Member for
17 years 10 monthsHi, I have manhours
Hi, I have manhours assigned to each activity, what I'm trying to get in spreadsheet is literally Schedule % Complete, not budgeted units or remaining units or BL budgeted units.
Member for
16 years 3 monthsplanned of what ?what is your
planned of what ?
what is your measuring stick
assign manhours to each activity then you will know the answer