Weekly schedule % complete.

Member for

16 years 3 months

your scheduled % complete is  from your basline schedule it is the total planned mahours for the project divided by the cumulatived manhours up to that month

i.e. total planned manhours 100 

total cumulative manhours at the end of that month = 10 

therefore 100/10= planned 10% complete

Member for

17 years 10 months

Hi, I have manhours assigned to each activity, what I'm trying to get in spreadsheet is literally Schedule % Complete, not budgeted units or remaining units or BL budgeted units.

Member for

16 years 3 months

planned of what ?

what is your measuring stick 

assign manhours to each activity then you will know the answer