wbs in primavera

4 replies [Last post]
craig roberts
User offline. Last seen 3 years 20 weeks ago. Offline
Joined: 3 Nov 2011
Posts: 11
Groups: None

Ive imported a msp file into p6 using mpx.

 

I inherited the msp but the wbs went down to activity level.

Ive imported it and the wbs only goes to summary level.

My client will be expecting the wbs to go to activity level like the msp plan he handed over to me to convert.

Replies

Zoltan Palffy
User offline. Last seen 3 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

xer transfer fixes all of this for you 

 https://xertransfer.com/

Celito Graca
User offline. Last seen 2 years 44 weeks ago. Offline
Joined: 21 Nov 2017
Posts: 4

Hi Sterling

 

Thanks for the link. Ive had some problems exporting and importing between MSP and P6 this looks like the solution to my problems.

 

https://www.profactaplan.com/

Sterling Gallagher
User offline. Last seen 1 year 7 weeks ago. Offline
Joined: 4 Oct 2019
Posts: 14
Groups: None

Hi Craig

 

There is a new tool available called XerTransfer that will allow you to import easily between both platforms.  The WBS in Both MSP & P6 will match.  It is compatible with Microsoft Project 2013, 2016 & 2019.  You can download a trila version with full functionality in the link https://xertransfer.com/ . As long as you have Microsoft Project 2013, 2016 or 2019 it will be a relatively quick process.

 

Regards

 

Sterling

Zoltan Palffy
User offline. Last seen 3 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

2 things

1st in the msp turn off the summaries prior to saving the file.

2nd save the fle in xml format and import the xml into p6