Budgeted Manhours and Budgeted Cost

Member for

16 years 3 months
Permalink

add a resource and make sure that calculate cost from units is NOT checked

then add the resource for alll of your activities then exort the resource and budget units and cost to excel

populate manhours and costs in excel

at the project level go to Projects and make sure that your project is open and highlighted

then on the resources tab make sure that under resource assignments that resources can be assigned to the same activity more than once is NOT checked 

then import the excel sheet back into P6