Planning, Scheduling & Programming Discussion add a resource and make sure add a resource and make sure that calculate cost from units is NOT checked then add the resource for alll of your activities then exort the resource and budget units and cost to excel populate manhours and costs in excel at the project level go to Projects and make sure that your project is open and highlighted then on the resources tab make sure that under resource assignments that resources can be assigned to the same activity more than once is NOT checked then import the excel sheet back into P6 Log in or register to post comments
add a resource and make sure add a resource and make sure that calculate cost from units is NOT checked then add the resource for alll of your activities then exort the resource and budget units and cost to excel populate manhours and costs in excel at the project level go to Projects and make sure that your project is open and highlighted then on the resources tab make sure that under resource assignments that resources can be assigned to the same activity more than once is NOT checked then import the excel sheet back into P6
add a resource and make sure
add a resource and make sure that calculate cost from units is NOT checked
then add the resource for alll of your activities then exort the resource and budget units and cost to excel
populate manhours and costs in excel
at the project level go to Projects and make sure that your project is open and highlighted
then on the resources tab make sure that under resource assignments that resources can be assigned to the same activity more than once is NOT checked
then import the excel sheet back into P6