Original duration not showing correctly in primavera

3 replies [Last post]
Raja Murugan
User offline. Last seen 6 years 48 weeks ago. Offline
Joined: 14 May 2017
Posts: 2
Groups: None

Hi

Original duration not showing correctly in primavera.

I have assigned 10 hours, 6 days work week calender.

Can anyone one help me?

Raja

Replies

Zoltan Palffy
User offline. Last seen 3 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

Ghous I already said that 

Ghous Mohideen M...
User offline. Last seen 6 years 24 weeks ago. Offline
Joined: 2 May 2017
Posts: 3
Groups: None
  • admin
  • admin preference
  • time periods

check your time for hours/day & other

Zoltan Palffy
User offline. Last seen 3 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

what is is showing ?

what is the duration TYPE ?

what is the activity TYPE ?

What are your settings under your users preferences Time units tab Hours Per Time Period?