Planning, Scheduling & Programming Discussion Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Thu, 2017-04-13 13:39 Permalink create a resource call it create a resource call it lumpsum make it labor and the default 8 hr/day make sure that calculate costs from units is NOT checked. filter for all of the activites that you want resources on then highlight them all right click and select Assign then resource and select lumpsum or the one you just created this will automatically multiply the duration by 8 to give you units ie. 5 days = 5*8=40 hours so thats 1 man on that activity for 5 days you change the unist to whatver you want or you can export the Budgeted Labor units to excel then change the units in excel and then import the correct units back into p6 after that select view show on bottom resource usage profile and you histogram is there Member for 8 years 8 months Member for 8 years 8 months Submitted by abraarukuk on Thu, 2017-04-13 06:45 Permalink someone reply,its urgent someone reply,its urgent Member for 8 years 8 months Member for 8 years 8 months Submitted by abraarukuk on Thu, 2017-04-13 06:45 Permalink primavera and excel i have primavera and excel i have Member for 8 years 8 months Member for 8 years 8 months Submitted by abraarukuk on Thu, 2017-04-13 06:44 Permalink primavera and excel i have primavera and excel i have Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Wed, 2017-04-12 13:18 Permalink what schedule package are you what schedule package are you using ? Log in or register to post comments
Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Thu, 2017-04-13 13:39 Permalink create a resource call it create a resource call it lumpsum make it labor and the default 8 hr/day make sure that calculate costs from units is NOT checked. filter for all of the activites that you want resources on then highlight them all right click and select Assign then resource and select lumpsum or the one you just created this will automatically multiply the duration by 8 to give you units ie. 5 days = 5*8=40 hours so thats 1 man on that activity for 5 days you change the unist to whatver you want or you can export the Budgeted Labor units to excel then change the units in excel and then import the correct units back into p6 after that select view show on bottom resource usage profile and you histogram is there
Member for 8 years 8 months Member for 8 years 8 months Submitted by abraarukuk on Thu, 2017-04-13 06:45 Permalink someone reply,its urgent someone reply,its urgent
Member for 8 years 8 months Member for 8 years 8 months Submitted by abraarukuk on Thu, 2017-04-13 06:45 Permalink primavera and excel i have primavera and excel i have
Member for 8 years 8 months Member for 8 years 8 months Submitted by abraarukuk on Thu, 2017-04-13 06:44 Permalink primavera and excel i have primavera and excel i have
Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Wed, 2017-04-12 13:18 Permalink what schedule package are you what schedule package are you using ?
Member for
16 years 3 monthscreate a resource call it
create a resource call it lumpsum make it labor and the default 8 hr/day
make sure that calculate costs from units is NOT checked.
filter for all of the activites that you want resources on
then highlight them all right click and select Assign then resource and select lumpsum or the one you just created
this will automatically multiply the duration by 8 to give you units ie. 5 days = 5*8=40 hours so thats 1 man on that activity for 5 days
you change the unist to whatver you want or you can export the Budgeted Labor units to excel then change the units in excel
and then import the correct units back into p6
after that select view show on bottom resource usage profile and you histogram is there
Member for
8 years 8 monthssomeone reply,its urgent
someone reply,its urgent
Member for
8 years 8 monthsprimavera and excel i have
primavera and excel i have
Member for
8 years 8 monthsprimavera and excel i have
primavera and excel i have
Member for
16 years 3 monthswhat schedule package are you
what schedule package are you using ?