Updating Existing Project for new Baseline

Member for

16 years 3 months

glad I could help 

Member for

9 years 6 months

Hi Mr Zolfan,

Your method works!! thanks for the reply.

Anderson

Member for

16 years 9 months

Please also Make sure the following:

- No filter has done in the update  especially,(in progress activities)

-in update , the option for thechnique  computing pecent comletion is custom  not 0/100

 

Good luck

Member for

16 years 3 months

assign the baseline then select update baseline and select costs