Planning, Scheduling & Programming Discussion Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Thu, 2017-04-13 13:55 Permalink glad I could help glad I could help Member for 9 years 6 months Member for 9 years 6 months Submitted by ndson89 on Wed, 2017-04-12 15:23 Permalink Hi Mr Zolfan,Your method Hi Mr Zolfan, Your method works!! thanks for the reply. Anderson Member for 16 years 9 months Member for 16 years 9 months Submitted by Amro Ahmed on Wed, 2017-04-12 07:52 Permalink Please also Make sure the Please also Make sure the following: - No filter has done in the update especially,(in progress activities) -in update , the option for thechnique computing pecent comletion is custom not 0/100 Good luck Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Mon, 2017-04-10 15:15 Permalink assign the baseline then assign the baseline then select update baseline and select costs Log in or register to post comments
Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Thu, 2017-04-13 13:55 Permalink glad I could help glad I could help
Member for 9 years 6 months Member for 9 years 6 months Submitted by ndson89 on Wed, 2017-04-12 15:23 Permalink Hi Mr Zolfan,Your method Hi Mr Zolfan, Your method works!! thanks for the reply. Anderson
Member for 16 years 9 months Member for 16 years 9 months Submitted by Amro Ahmed on Wed, 2017-04-12 07:52 Permalink Please also Make sure the Please also Make sure the following: - No filter has done in the update especially,(in progress activities) -in update , the option for thechnique computing pecent comletion is custom not 0/100 Good luck
Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Mon, 2017-04-10 15:15 Permalink assign the baseline then assign the baseline then select update baseline and select costs
Member for
16 years 3 monthsglad I could help
glad I could help
Member for
9 years 6 monthsHi Mr Zolfan,Your method
Hi Mr Zolfan,
Your method works!! thanks for the reply.
Anderson
Member for
16 years 9 monthsPlease also Make sure the
Please also Make sure the following:
- No filter has done in the update especially,(in progress activities)
-in update , the option for thechnique computing pecent comletion is custom not 0/100
Good luck
Member for
16 years 3 monthsassign the baseline then
assign the baseline then select update baseline and select costs