In Asta Powerproject there is a button which says "Start on Next Day" so if the task duration ends at 14:00 hrs the next task starts on 08:00 next day and it remains critical.
I assume that this is P6 so go to edit users preference and turn the time on by going to the dates tab and at the bottom select Time 12 Hour.
Also click on the Time Units tab and change the decimals to 2 for unit of time and the Durations format.
Now go to the Projects Directory and select view show on bottom Project Details
make sure that you project is highlighted and go to the Date tab in the Planned Start box make sure that the TIME is 8:00 am or the earliest TIMES in all of the calendars that you are using.
IN the Data Date box make sure that the TIME is 8:00 am or the earliest TIME (or hour) in all of the calendars that you are using.
IN the Must Finish By Date box make sure that TIME is 5:00 pm or the LATEST TIME (or hour) in all of the calendars that you are using.
Go back to the activities directory filter for start milestones change and of the Primary Constrained Date TIME to 8:00 am or the earliest TIME (or hour) in all of the calendars that you are using.
filter for finish milestones change and of the Primary Constrained Date TIME to 5:00 PM or the latest TIME (or hour) in all of the calendars that you are using.
look at ALL of the original durations and remaining durations if any are in fractions of a day like 1.5 or 0.5 change these to whole numbers.
Look at your calendars and make sure that the TIMES are correct in all of the calendars that you are using for that project.
Press F9 and make sure that the TIME is 8:00 am or the earliest TIME (or hour) in all of the calendars that you are using.
Member for
16 years 3 monthssan TS glad I could helpMike
san TS glad I could help
Mike I am not sure why you are answering a P6 question with an ASTA answer it does no one any good.
Thats like me asking what temperature is in one city and you giving me the temperature of a city in a different conuntry.
Apples and Oranges
Member for
19 years 10 monthsIn Asta Powerproject there is
In Asta Powerproject there is a button which says "Start on Next Day" so if the task duration ends at 14:00 hrs the next task starts on 08:00 next day and it remains critical.
Best regards
Mike Testro
Member for
13 years 10 monthsThanks a lot,Zoltan. BR,San
Thanks a lot,Zoltan.
BR,
San
Member for
16 years 3 monthsI assume that this is P6 so
I assume that this is P6 so go to edit users preference and turn the time on by going to the dates tab and at the bottom select Time 12 Hour.
Also click on the Time Units tab and change the decimals to 2 for unit of time and the Durations format.
Now go to the Projects Directory and select view show on bottom Project Details
make sure that you project is highlighted and go to the Date tab in the Planned Start box make sure that the TIME is 8:00 am or the earliest TIMES in all of the calendars that you are using.
IN the Data Date box make sure that the TIME is 8:00 am or the earliest TIME (or hour) in all of the calendars that you are using.
IN the Must Finish By Date box make sure that TIME is 5:00 pm or the LATEST TIME (or hour) in all of the calendars that you are using.
Go back to the activities directory filter for start milestones change and of the Primary Constrained Date TIME to 8:00 am or the earliest TIME (or hour) in all of the calendars that you are using.
filter for finish milestones change and of the Primary Constrained Date TIME to 5:00 PM or the latest TIME (or hour) in all of the calendars that you are using.
look at ALL of the original durations and remaining durations if any are in fractions of a day like 1.5 or 0.5 change these to whole numbers.
Look at your calendars and make sure that the TIMES are correct in all of the calendars that you are using for that project.
Press F9 and make sure that the TIME is 8:00 am or the earliest TIME (or hour) in all of the calendars that you are using.