I am not a Primavera P6 user but at times receive P6XER files to be transferred to my software so I do not know all the implications of the following suggestion with regard to resource leveling. I receive the XER files but do not have P6.
Try resource lag and resource duration, for example if activity duration is 10 days use 9 days for resource lag and one day for resource duration. It should work well for fixed duration activities as long as you do not make changes to total activity duration. Workarounds should always be of last resort.
Member for
21 years 7 monthsI am not a Primavera P6 user
I am not a Primavera P6 user but at times receive P6 XER files to be transferred to my software so I do not know all the implications of the following suggestion with regard to resource leveling. I receive the XER files but do not have P6.
Try resource lag and resource duration, for example if activity duration is 10 days use 9 days for resource lag and one day for resource duration. It should work well for fixed duration activities as long as you do not make changes to total activity duration. Workarounds should always be of last resort.
https://www.youtube.com/watch?v=KukSYuCFAS8
Good Luck
Member for
9 years 3 monthsPrimavera P6
Primavera P6