Does the construction materials procurement time get entered into the project plan?

Member for

9 years 11 months

Much appreciated. All those things you insert into the plan? interesting.. stock plan?? 1 day?? what's that?

Member for

19 years 10 months

Hi Timothy

Yes.

Its not just procurement - the sequence is usually: - Assumed durations - working days - will vary from package to package.

Design Complete  - Milestone 0

Tender 20

Place Order 5

Workshop drawings 10

Approval 5

Manufacture 25

Delivery 2

Stock Take 1

Ready to install - milestone 0

The last milestone is linked to the start of the first task and the tasks are set ALAP.

This shows the latest date for the design issue.

Best regards

Mike T.