Planning, Scheduling & Programming Discussion Member for 9 years 11 months Member for 10 years Submitted by Ronin63 on Sat, 2016-07-02 17:42 Permalink Much appreciated. All those Much appreciated. All those things you insert into the plan? interesting.. stock plan?? 1 day?? what's that? Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Sat, 2016-07-02 13:47 Permalink Hi TimothyYes.Its not just Hi Timothy Yes. Its not just procurement - the sequence is usually: - Assumed durations - working days - will vary from package to package. Design Complete - Milestone 0 Tender 20 Place Order 5 Workshop drawings 10 Approval 5 Manufacture 25 Delivery 2 Stock Take 1 Ready to install - milestone 0 The last milestone is linked to the start of the first task and the tasks are set ALAP. This shows the latest date for the design issue. Best regards Mike T. Log in or register to post comments
Member for 9 years 11 months Member for 10 years Submitted by Ronin63 on Sat, 2016-07-02 17:42 Permalink Much appreciated. All those Much appreciated. All those things you insert into the plan? interesting.. stock plan?? 1 day?? what's that?
Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Sat, 2016-07-02 13:47 Permalink Hi TimothyYes.Its not just Hi Timothy Yes. Its not just procurement - the sequence is usually: - Assumed durations - working days - will vary from package to package. Design Complete - Milestone 0 Tender 20 Place Order 5 Workshop drawings 10 Approval 5 Manufacture 25 Delivery 2 Stock Take 1 Ready to install - milestone 0 The last milestone is linked to the start of the first task and the tasks are set ALAP. This shows the latest date for the design issue. Best regards Mike T.
Member for
9 years 11 monthsMuch appreciated. All those
Much appreciated. All those things you insert into the plan? interesting.. stock plan?? 1 day?? what's that?
Member for
19 years 10 monthsHi TimothyYes.Its not just
Hi Timothy
Yes.
Its not just procurement - the sequence is usually: - Assumed durations - working days - will vary from package to package.
Design Complete - Milestone 0
Tender 20
Place Order 5
Workshop drawings 10
Approval 5
Manufacture 25
Delivery 2
Stock Take 1
Ready to install - milestone 0
The last milestone is linked to the start of the first task and the tasks are set ALAP.
This shows the latest date for the design issue.
Best regards
Mike T.