Planning, Scheduling & Programming Discussion Much appreciated. All those Much appreciated. All those things you insert into the plan? interesting.. stock plan?? 1 day?? what's that? Hi TimothyYes.Its not just Hi Timothy Yes. Its not just procurement - the sequence is usually: - Assumed durations - working days - will vary from package to package. Design Complete - Milestone 0 Tender 20 Place Order 5 Workshop drawings 10 Approval 5 Manufacture 25 Delivery 2 Stock Take 1 Ready to install - milestone 0 The last milestone is linked to the start of the first task and the tasks are set ALAP. This shows the latest date for the design issue. Best regards Mike T. Log in or register to post comments
Much appreciated. All those Much appreciated. All those things you insert into the plan? interesting.. stock plan?? 1 day?? what's that?
Hi TimothyYes.Its not just Hi Timothy Yes. Its not just procurement - the sequence is usually: - Assumed durations - working days - will vary from package to package. Design Complete - Milestone 0 Tender 20 Place Order 5 Workshop drawings 10 Approval 5 Manufacture 25 Delivery 2 Stock Take 1 Ready to install - milestone 0 The last milestone is linked to the start of the first task and the tasks are set ALAP. This shows the latest date for the design issue. Best regards Mike T.
Much appreciated. All those
Much appreciated. All those things you insert into the plan? interesting.. stock plan?? 1 day?? what's that?
Hi TimothyYes.Its not just
Hi Timothy
Yes.
Its not just procurement - the sequence is usually: - Assumed durations - working days - will vary from package to package.
Design Complete - Milestone 0
Tender 20
Place Order 5
Workshop drawings 10
Approval 5
Manufacture 25
Delivery 2
Stock Take 1
Ready to install - milestone 0
The last milestone is linked to the start of the first task and the tasks are set ALAP.
This shows the latest date for the design issue.
Best regards
Mike T.