No issues. Your Sujjestion is takne into account but I would prefer a schedule to be a little detailed so as to know whose fault it is Vendor, Contractor or Client which you cannot know by putting just a Milestone (Who is responsible for the Milestone).
I (Contractor) work on EPC projects and I split the Procurement Task according to the Material as its all by different vendors example,
Pump
Tanks
Generator
Pipes and Fittings
Cables
Instruments
etc.
We split it according to Material (Vendors) so as to monitor which item is delayed and what will affect the Project completion. Whom to Push like usually Bid Evaluation Award (Contractor), Manufacturing (Vendor) and Delivery (Contractor).
So by spliting it up we can Alert as to whose part is the delay is The Vendor , Client or Contractor.
Hi Raymund,
Usually Manufacturing and Delivery Period can be monitored as the Vendor would say that example They need 22 Weeks for Manufacturing and Delivery (Usually by the one who places Purchase Order - Contractor) can be monitored like we (Contractor) on gerneral note know that it would take a minimum of 6 Weeks of delivery from USA or EUROPE to Middle East.
So we would know when the Manufacturing and delivery would be finished. We can Alert our team (Procurement) to look at if its finished and is it shipped. All this points would defenitly help you out.
Regards
Jithin
Member for
15 years 11 months
Member for15 years11 months
Submitted by Raymund de Laza on Thu, 2016-03-24 14:26
My concern is in updating the Manufacturing progress. During those period of Manufacturing when there is need to update the Schedule then the Progress will just be computed as number of days passed vs remaining days.
My Suggestion as Milestone is that the Contractor just wait for the delivery Date and if arrived then update the schedule accordingly.
Just a suggestion.
Member for
15 years 11 months
Member for15 years11 months
Submitted by Raymund de Laza on Thu, 2016-03-24 13:21
Its better to put 3 task for a procurement item as minimum.
1) Bid, Evaluation and Award2) Complete Manufacturing and Final Inspection 3) Delivery - Delivery duration is the time to ship / airlift or any means of transportation of material from the manufacturing location.
One more option is which is little bit more detailed,
1) Prepare / Issue MR2) Recieve Bid 3) Complete Technical Evaluation and Submit TBE for Company Approval 4) Receive Company Approval 5) Issue FOA / FOA/Letter of Award 6) Manufacturing 7) Delivery
With this you can properly monitor where the delay is and what is the effect.
Member for
14 years 7 monthsHi Raymund,No issues. Your
Hi Raymund,
No issues. Your Sujjestion is takne into account but I would prefer a schedule to be a little detailed so as to know whose fault it is Vendor, Contractor or Client which you cannot know by putting just a Milestone (Who is responsible for the Milestone).
Regards
Jithin
Member for
14 years 7 monthsHi Eugene,I (Contractor) work
Hi Eugene,
I (Contractor) work on EPC projects and I split the Procurement Task according to the Material as its all by different vendors example,
Pump
Tanks
Generator
Pipes and Fittings
Cables
Instruments
etc.
We split it according to Material (Vendors) so as to monitor which item is delayed and what will affect the Project completion. Whom to Push like usually Bid Evaluation Award (Contractor), Manufacturing (Vendor) and Delivery (Contractor).
So by spliting it up we can Alert as to whose part is the delay is The Vendor , Client or Contractor.
Hi Raymund,
Usually Manufacturing and Delivery Period can be monitored as the Vendor would say that example They need 22 Weeks for Manufacturing and Delivery (Usually by the one who places Purchase Order - Contractor) can be monitored like we (Contractor) on gerneral note know that it would take a minimum of 6 Weeks of delivery from USA or EUROPE to Middle East.
So we would know when the Manufacturing and delivery would be finished. We can Alert our team (Procurement) to look at if its finished and is it shipped. All this points would defenitly help you out.
Regards
Jithin
Member for
15 years 11 monthsJithin,My concern is in
Jithin,
My concern is in updating the Manufacturing progress. During those period of Manufacturing when there is need to update the Schedule then the Progress will just be computed as number of days passed vs remaining days.
My Suggestion as Milestone is that the Contractor just wait for the delivery Date and if arrived then update the schedule accordingly.
Just a suggestion.
Member for
15 years 11 monthsI suggest to use a milestone
I suggest to use a milestone for the Delivery date needed prior to Installation/Execution. Then use ALAP constraint.
Manufacturing and Delivery Time Period can not be Monitored.
Member for
9 years 7 monthsHi Jithin,Thanks a lot!
Hi Jithin,
Thanks a lot! Sounds advice that goes beyond what I have expected to get.
So, I should make task by vendor a task.
To think further on it, is there any disadvantage to use set lead time on milestone for delivery date?
Thanks.
Member for
14 years 7 monthsHi Eugene,Its better to put 3
Hi Eugene,
Its better to put 3 task for a procurement item as minimum.
1) Bid, Evaluation and Award 2) Complete Manufacturing and Final Inspection 3) Delivery - Delivery duration is the time to ship / airlift or any means of transportation of material from the manufacturing location.
One more option is which is little bit more detailed,
1) Prepare / Issue MR 2) Recieve Bid 3) Complete Technical Evaluation and Submit TBE for Company Approval 4) Receive Company Approval 5) Issue FOA / FOA/Letter of Award 6) Manufacturing 7) Delivery