Progressing a Schedule Before Baselining

1 reply [Last post]
Jordan Thomas
User offline. Last seen 8 years 10 weeks ago. Offline
Joined: 2 Mar 2015
Posts: 3
Groups: None

Hello,

After building the project schedule, but before reaching an agreed-to baseline with the client, is it ok to enter progress dates into activities that have taken place in the time between putting the schedule together and reaching the agreed-upon baseline with the client? Or is there a different standard method for doing this?

Replies

Jerome Odeh
User offline. Last seen 2 weeks 1 day ago. Offline
Joined: 19 Jan 2004
Posts: 102

Hi Jordan,

I'll keep updating the schedule to reflect actuals but without assigning a % complete until the schedule is submitted to the client for approval.

In other words, all activities will appear as Planned Dates but those between Project Start Date and Time Now will reflect reality.

  =jerome
http://plannerstips.blogspot.co.uk/