Planning, Scheduling & Programming Discussion Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Tue, 2015-07-14 13:48 Permalink need more info1. Did you look need more info 1. Did you look at the TYPE of activity ? Level of efforts or summary wbs typs of activities are based on the underlaying activities. 2. I would hope that it is showing the critical path in p6 that is what the program is all about hence the name critical ptha method CPM 3. Why does the schedule have negative float either becasue you are behind schedule or you have not progressed your schedule correctly. 4. I do not undrstand the title of the post unit % complete not able to update in Status bar you mentioned nothing about units have you checked your calculations settings ? when updating actual units or cost subtract actual for at completion also recalculate actual units and cost when duration % complete changes and Link actual and actaul this period units and cost Log in or register to post comments
Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Tue, 2015-07-14 13:48 Permalink need more info1. Did you look need more info 1. Did you look at the TYPE of activity ? Level of efforts or summary wbs typs of activities are based on the underlaying activities. 2. I would hope that it is showing the critical path in p6 that is what the program is all about hence the name critical ptha method CPM 3. Why does the schedule have negative float either becasue you are behind schedule or you have not progressed your schedule correctly. 4. I do not undrstand the title of the post unit % complete not able to update in Status bar you mentioned nothing about units have you checked your calculations settings ? when updating actual units or cost subtract actual for at completion also recalculate actual units and cost when duration % complete changes and Link actual and actaul this period units and cost
Member for
16 years 3 monthsneed more info1. Did you look
need more info
1. Did you look at the TYPE of activity ?
Level of efforts or summary wbs typs of activities are based on the underlaying activities.
2. I would hope that it is showing the critical path in p6 that is what the program is all about hence the name critical ptha method CPM
3. Why does the schedule have negative float either becasue you are behind schedule or you have not progressed your schedule correctly.
4. I do not undrstand the title of the post
unit % complete not able to update in Status bar
you mentioned nothing about units
have you checked your calculations settings ?
when updating actual units or cost
subtract actual for at completion
also recalculate actual units and cost when duration % complete changes
and Link actual and actaul this period units and cost