unit % complete not able to update in Status bar

Member for

16 years 3 months

need more info

1. Did you look at the TYPE of activity ?

Level of efforts or summary wbs typs of activities are based on the underlaying activities.

2. I would hope that it is showing the critical path in p6 that is what the program is all about hence the name critical ptha method CPM 

3. Why does the schedule have negative float either becasue you are behind schedule or you have not progressed your schedule correctly. 

4. I do not undrstand the title of the post 

unit % complete not able to update in Status bar

you mentioned nothing about units 

have you checked your calculations settings ?

when updating actual units or cost 

subtract actual for at completion

also recalculate actual units and cost when duration % complete changes

and Link actual and actaul this period units and cost