Resetting the Baseline on a Progress with Progress Applied?

Member for

16 years 3 months

if you do not have a baseline you will have to copy the current schedule and then destatus the schedule to get an unprogressed schedule ot use as your baseline.

if you want a step by step process see my post at the link below.

 

 http://pmsite.com/forums/viewthread/3064/