Time schedule in tender phase

2 replies [Last post]
haytham saad
User offline. Last seen 2 years 24 weeks ago. Offline
Joined: 12 Apr 2013
Posts: 24
HI All i'm currently working on a schedule for tender phase for a shopping mall my company is participating in, the problem that my managers are requesting detailed schedule and detailed activities and also asking if we could provide a resource loaded schedule , in my opinion the tender phase is all about the time frame for project and the key milestone and the sequence of work, here comes the question :D what do you think the best practice for providing time schedule in tender phase ??? if any one can provide me a sample of his/her tender schedule as a guide that will be great.RegardsHaytham saad

Replies

haytham saad
User offline. Last seen 2 years 24 weeks ago. Offline
Joined: 12 Apr 2013
Posts: 24

Dear mike

Thanks for ur reply, the problem is that the scope of work is wide from civil:concrete-steel works & Electrical & Mechanical andit will be difficuilt  to reflect all the BOQ items as Activities in this phase , also i need to ask u waht other report should i present with my schhedule ??

Thanks

Mike Testro
User offline. Last seen 5 weeks 4 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Haytham

A tender programme should be a bottom up level 4 in as much detail as possible.

Its purpose is to:

1. Check if the construction period is feasible.

2. Assist the estimator on plant and scaffolding durations

3. Carry out what if scenarios

This cannot be done in a level 3 programme.

And it must be resource loaded so that the durations reflect the cost plan.

A shopping mall is not a complex structure and a skilled and experienced planner should have a programme for first review in about 3 days.

Best regards

Mike Testro