Thanks for ur reply, the problem is that the scope of work is wide from civil:concrete-steel works & Electrical & Mechanical andit will be difficuilt to reflect all the BOQ items as Activities in this phase , also i need to ask u waht other report should i present with my schhedule ??
Member for
12 years 6 monthsDear mikeThanks for ur reply,
Dear mike
Thanks for ur reply, the problem is that the scope of work is wide from civil:concrete-steel works & Electrical & Mechanical andit will be difficuilt to reflect all the BOQ items as Activities in this phase , also i need to ask u waht other report should i present with my schhedule ??
Thanks
Member for
19 years 10 monthsHi HaythamA tender programme
Hi Haytham
A tender programme should be a bottom up level 4 in as much detail as possible.
Its purpose is to:
1. Check if the construction period is feasible.
2. Assist the estimator on plant and scaffolding durations
3. Carry out what if scenarios
This cannot be done in a level 3 programme.
And it must be resource loaded so that the durations reflect the cost plan.
A shopping mall is not a complex structure and a skilled and experienced planner should have a programme for first review in about 3 days.
Best regards
Mike Testro