Time schedule in tender phase

Member for

12 years 6 months

Dear mike

Thanks for ur reply, the problem is that the scope of work is wide from civil:concrete-steel works & Electrical & Mechanical andit will be difficuilt  to reflect all the BOQ items as Activities in this phase , also i need to ask u waht other report should i present with my schhedule ??

Thanks

Member for

19 years 10 months

Hi Haytham

A tender programme should be a bottom up level 4 in as much detail as possible.

Its purpose is to:

1. Check if the construction period is feasible.

2. Assist the estimator on plant and scaffolding durations

3. Carry out what if scenarios

This cannot be done in a level 3 programme.

And it must be resource loaded so that the durations reflect the cost plan.

A shopping mall is not a complex structure and a skilled and experienced planner should have a programme for first review in about 3 days.

Best regards

Mike Testro